Key US natural gas pipeline delayed as costs grow to $6.6 billion

A major US natural gas pipeline project has been delayed again as developer Equitrans Midstream Corp. pursues new permits for the troubled conduit.

The Mountain Valley Pipeline is now estimated to start up in the second half of 2023 and will cost $6.6 billion, the company said Tuesday in a statement. That’s up from a previous forecast of $6.2 billion.

For the latest headlines, follow our Google News channel online or via the app.

Until late last year, Equitrans expected the pipeline to start operating by this summer. It was originally expected to be in service in 2018, and the cost estimate has roughly doubled since the project was announced in 2014.

Equitrans is trying to get new permits for the project after a US appeals court earlier this year tossed the federal government’s approval for Mountain Valley to go through Jefferson National Forest in the Virginias.

Mountain Valley, which is more than 90 percent complete, aims to connect drillers in the gas-rich Marcellus and Utica shale basins with major East Coast markets.

Other projects in the region were scrapped amid fierce opposition from environmental groups, including proposals from Dominion Energy Inc., Duke Energy Corp. and Williams Cos.

Equitrans, which owns 48 percent of the 488-kilometer conduit, has funded about $2.6 billion of the project and expects to spend $3.4 billion.

Read more:

BP expects to pay up to 1 bln pounds in UK taxes on its 2022 profits

Italy aims to cut off dependence on Russia gas by H2 2024: Minister

Qatar reclaims crown from US as world’s top LNG exporter

Leave a Reply

Your email address will not be published. Required fields are marked *

Trending

Exit mobile version